Notes from infrastructure construction meeting 8/27/26

Streets reconstruction continues in preparation for paving later this month.

1. Pay Application 18 is for $208,206.04. $70,689.15 is the City share.

2. Progress Report and Upcoming Work: 

a. Street reconstruction was completed on Logan Ave from 11th St to 14th St, 7th St, 8…